Presentation - Arlingtonva

Report 9 Downloads 103 Views
Agenda 1. 2. 3. 4. 5.

SPRC #3 Follow-Up Items Residential Building Updates Macy’s Air-Rights Office Updates Signage Presentation Construction Phasing / Sequencing

28 Sep 2015 SPRC #4 Pg 1

SPRC 3 Follow-Up: • • • • • •

Curb Side Management / Streetscape Follow-Up Randolph Street Entry Update West Plaza Elements for Children Residential Parking Glebe Road Enhancements

SPRC 3 Follow-Up – Agenda

28 Sep 2015 SPRC #4 Pg 2

SPRC 3 Follow-Up – Curb Side Management

28 Sep 2015 SPRC #4 Pg 3

28 Sep 2015 SPRC #4

SPRC 3 Follow-Up – Curb Side Management

Pg 4 Key

1

5

7 10’ CLEAR POTENTIAL FEATURE ELEMENTS

6 8

2 3 8

28 Sep 2015 SPRC #4

Streetscape – Wilson Boulevard

Pg 5 Key

28 Sep 2015 SPRC #4

SPRC 3 Follow-Up – Curb Side Management

Pg 6 Key

POTENTIAL FEATURE ELEMENT

2

5

10’ CLEAR 6

3 8

1

3

28 Sep 2015 SPRC #4

Streetscape – Wilson Boulevard

Pg 7 Key

28 Sep 2015 SPRC #4

SPRC 3 Follow-Up – Curb Side Management

Pg 8 Key

5 1

3 5

2

7

10’ CLEAR

8 6

2

28 Sep 2015 SPRC #4

Streetscape – Wilson Boulevard

Pg 9 Key

RES LOBBY

28 Sep 2015 SPRC #4

SPRC 3 Follow-Up – Curb Side Management

Pg 10 Key

8’ CLEAR PATH

Future Pedestrian Pathway

28 Sep 2015 SPRC #4

Streetscape - Randolph

Pg 11 Key

28 Sep 2015 SPRC #4

SPRC 3 Follow-Up – Curb Side Management

Pg 12 Key

4

28 Sep 2015 SPRC #4

Streetscape – Glebe Road

Pg 13 Key

Connection to Mews: • • • • •

6’ Wide with 10’ Ceiling Security Monitored Fully HC Accessible Same hours as Wilson Bridge Designed to be Welcoming and Well Lit

4040 WILSON BLVD (Under Const)

Decorative Screening

675 N Randolph (DARPA)

Clearly Defined Pathway

Abundance of Lighting

Connection to Mews

28 Sep 2015 SPRC #4

SPRC 3 Follow-Up – Randolph Street Connectivity

Pg 14 Key

Connection to Mews

28 Sep 2015 SPRC #4

SPRC 3 Follow-Up – Randolph Street Connectivity

Pg 15 Key

28 Sep 2015 SPRC #4

SPRC 3 Follow-Up – West Plaza

Pg 16 Key

28 Sep 2015 SPRC #4

SPRC 3 Follow-Up – West Plaza

Pg 17 Key

Engaging Art Elements

Chalkboard Figure

Tom Otterness Artwork

Subtle Incorporation

28 Sep 2015 SPRC #4

SPRC 3 Follow-Up – Engaging Art / Elements for Children

Pg 18 Key

Interactive Lighting

Temporary Installations

Integrated Furnishings

28 Sep 2015 SPRC #4

SPRC 3 Follow-Up – Interactive Lighting / Elements for Children

Pg 19 Key

Residential Parking: • 288 automobile spaces + 8 motorcycle spaces are provided for 406 apartments units • 0.7 automobile parking spaces per apartment (.72 ratio including motorcycles) • Walk score / Data supports this ratio: • Walk Score: 95 ("Walkers Paradise - Daily errands do not require a car.") • Transit Score: 77 ("Excellent Transit - Transit is convenient for most trips.") • Bike Score: 80 ("Very Bikable - Flat as a pancake, excellent bike lanes.")

• TDM includes car-sharing services in the garage • If additional spaces are needed, possible partnership with adjacent and under-utilized County Garage for residents and/or visitors to minimize need for on-street parking

SPRC 3 Follow-Up – Residential Parking

28 Sep 2015 SPRC #4 Pg 20

County Garage Utilization: • 2912 Total Spaces Available; commuter, office, retail uses • In 2012 the garage was 76% occupied at peak • More than 680 spaces available • In 2015 the garage was 64% utilized at peak • More than 1,040 spaces available 1,043

Time 9:00 AM 1:00 PM 5:00 PM

Occupied Spaces 1,426 2,227 1,476

2012 Available Spaces 1,486 685 1,436

Percent Occupied 49% 76% 51%

Occupied Spaces 1,288 1,869 1,232

2015 Available Spaces 1,624 1,043 1,680

SPRC 3 Follow-Up – Residential Parking

Percent Occupied 44% 64% 42%

• Office and retail peak is the middle of the day • Residential peak parking is the middle of the night • Allows for shared parking

Total Spaces 2,912 2,912 2,912

28 Sep 2015 SPRC #4 Pg 21

County Garage Proximity: To Res Lobby (at grade)

Down Escalator

• A connection provides access from the adjacent County Garage • Third Level of Garage = Second Level Retail Concourse • A direct pathway allows easy access to the residential lobby

Direct Pathway from Garage to Res Entry at Mews

2nd Level Concourse also same as

(3rd Level Garage)

County Garage

County Garage

28 Sep 2015 SPRC #4

SPRC 3 Follow-Up – Residential Parking

Pg 22 Key

CONTEXT ELEVATION Dedicated Office Entry

New Mall Entry

PLAN VIEW

SPRC 3 Follow-up – Glebe Enhancements

28 Sep 2015 SPRC #4 Pg 23

Continuous Tree Planting Concrete Paving

Granite Paving

Light Totems

Street Furniture

Streetscape elements match treatment at Wilson Blvd: • Continuous Street Tree Planting • Sidewalk Paving • Totem Concept • Street Furniture

Separate Entrances are now provided for retail and office uses

Glebe Road Existing parking has been removed and sidewalk extended

Off Peak Parking

Café Seating Zones

Granite ‘carpet’ at pedestrian entrances

28 Sep 2015 SPRC #4

SPRC 3 Follow-up – Glebe Enhancements

Pg 24 Key

28 Sep 2015 SPRC #4

SPRC 3 Follow-up – Glebe Enhancements

Pg 25 Key

Residential Building • • • • • •

22 Story Building 2 Retail Levels, 66,035 gsf (includes 13,740 gsf in potential future mezzanine area at level 2) 20 Residential Levels, 406 Rental Apartment Units 4 Underground Parking Levels, 288 Automobile Spaces + 8 Motorcycle Spaces Readily accessible from adjacent County garage LEED Silver

Residential Building

28 Sep 2015 SPRC #4 Pg 26

East Plaza

Access to County Garage (via escalator to Level 2)

N Randolph St

Residential Entry

KEY RETAIL

Outdoor Residential Amenity

KEY 2BR APT 1BR +DEN APT

PUBLIC CORR

1BR APT

RES LOBBY

1BR 2 STORY APT

Mews Shortcut

RES SUPPORT SERVICE

STUDIO APT

Parking & Service

Typical Residential Floor

Ground Floor

28 Sep 2015 SPRC #4

Residential Building – Ground and Typical Levels

Pg 27 Key

OH Door

N Randolph St

Retail Service

N Randolph St

Residential Service

Residential Parking N

Parking & Service (From Abv)

P1

P2, (P3 & P4 sim) 28 Sep 2015 SPRC #4

Residential Building – Parking Levels

Pg 28 Key

28 Sep 2015 SPRC #4

Residential Building – Exterior Views

Pg 29 Key

Macy’s Air Rights Office Building • • • •

Upgrade existing three office levels above Macy’s New office entry towers at Wilson and Glebe Interior courtyard for office users Three Office Levels plus entry towers: 159,533 SF

Macy’s Office Bldg

28 Sep 2015 SPRC #4 Pg 30

Macy’s Office Building – First, Fourth, and Fifth Floor Plans

28 Sep 2015 SPRC #4 Pg 31 Key

Macy’s Office Building – Mezzanine, Sixth and Roof Plans

28 Sep 2015 SPRC #4 Pg 32 Key

Wilson Blvd

Glebe Road

Macy’s Office Building – North-South Building Section

28 Sep 2015 SPRC #4 Pg 33 Key

View from Wilson Boulevard

Macy’s Office Building – Exterior Views

View from Glebe Road

28 Sep 2015 SPRC #4 Pg 34

Signage Deeply expressive and complimentary visual elements are the hallmark of many highly successful commercial shopping districts globally, nationally and regionally A hierarchy of environmental graphic and signage elements incorporated into Ballston Quarter include: 1. 2. 3.

4. 5. 6.

District Identity Signage Image Projection Tenant Expression Zone 3a. Tenant Transparency 3b. Retail Character Imagery 3c. Tenant Display Tenant Signage Theatrical Event Projection Project Signage/Wayfinding

Signage

28 Sep 2015 SPRC #4 Pg 35

Signage

28 Sep 2015 SPRC #4 Pg 36

Signage

28 Sep 2015 SPRC #4 Pg 37

Signage

28 Sep 2015 SPRC #4 Pg 38

Signage

28 Sep 2015 SPRC #4 Pg 39

Signage

28 Sep 2015 SPRC #4 Pg 40

Signage

28 Sep 2015 SPRC #4 Pg 41

Signage

28 Sep 2015 SPRC #4 Pg 42

Signage

28 Sep 2015 SPRC #4 Pg 43

Signage

28 Sep 2015 SPRC #4 Pg 44

Construction Phasing and Sequencing

Construction Phasing

28 Sep 2015 SPRC #4 Pg 45

Phase 1 Key Activities: • Site is Fenced Off • MFS Store Demo Begins • Mall remains open

Construction Phasing

28 Sep 2015 SPRC #4 Pg 46

Phase 1A Key Activities: • Mall site is fenced off • Wilson covered walkway is installed • West Plaza demo begins • Mall Interior construction starts • Mall dock and portions of mall remain open • Bridge closes

Construction Phasing

28 Sep 2015 SPRC #4 Pg 47

Phase 1B Key Activities: • Bridge demolition begins • Demo occurs over three consecutive weekends: • Weekend 1: Skin • Weekend 2: Structure • Weekend 3: Structure

• Wilson is closed during the three weekends • Traffic is restored during interim weekdays • Mall dock and portions of mall remain open

Construction Phasing

28 Sep 2015 SPRC #4 Pg 48

Phase 1C Key Activities: • Bridge construction occurs • Interim Wilson shutdowns req’d for bridge construction • Bridge re-opens Dec 2017 • Mall dock and portions of mall remain open

Construction Phasing

28 Sep 2015 SPRC #4 Pg 49

Phase 2 Key Activities: • Res Garage Excavation • Truck loop: • • • •

395 to Glebe East on Wilson from Glebe South on Randolph Stacking and loading area inside site fencing on Randolph • SE on Glebe directly to 395

Construction Phasing

28 Sep 2015 SPRC #4 Pg 50

Phase 2A Key Activities: • Retail ‘skin’ activities ongoing on Wilson • West Plaza construction starts • Mall interior construction is ongoing • Mall dock and portions of mall remain open • Macy’s Office site mobilization starts Jan 2017

Construction Phasing

28 Sep 2015 SPRC #4 Pg 51

Phase 3 Key Activities: • Tower Concrete Structure • Concrete Truck loop: • • • •

395 to Glebe East on Wilson from Glebe South on Randolph Stacking and off-loading area inside site fencing on Randolph • SE on Glebe directly to 395

Construction Phasing

28 Sep 2015 SPRC #4 Pg 52

Phase 3A Key Activities: • Demolition at East Mews area starts • West Plaza construction continues • Mall Interior construction is ongoing • Mall dock and portions of mall remain open • Macy’s office const ongoing

Construction Phasing

28 Sep 2015 SPRC #4 Pg 53

Phase 4A Key Activities: • Wilson Blvd roadway realignment occurs • Interior mall construction nearing completion • Macy’s Office construction nearing completion

Construction Phasing

28 Sep 2015 SPRC #4 Pg 54

Phase 4 Key Activities: • Exterior skin applied to residential building • Interior construction ongoing at residential bldg • Retail completion May 2018 • Macy’s office completion Apr 2018 • Randolph streetscape completes Sep 2018 • Residential completion 4Q 2018

Construction Phasing

28 Sep 2015 SPRC #4 Pg 55