Replacement of N. Carlin Springs Road Bridge over ... - Arlingtonva

Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance of Travel (MOT) plans

October 2017

Project Elements • Removal of existing bridge span over George Mason Drive • Construction of new bridge with four travel lanes, bike lanes, wider sidewalks, jointless deck, higher clearance and refurbished bridge abutments • Installation of new sanitary sewer line under N. Abingdon Street and Carlin Springs Road • Site restoration & enhancement

5’

25.5’

4’

25.5’

5’

Existing Centerline

Existing Cross Section – 65’ Wide 8’

5’

11’

10.5’

10.5’

11’

Final Centerline

Planned Cross Section – 69’ Wide

5’

8’

New Bridge’s Design

Projected Schedule • November 1 _ Contractor’s “Notice to Proceed” • December 1– Demolition & New Construction begins • Fall 2019 – Construction complete • Spring 2020 – Landscape restoration

Phase 1 Work & Maintenance of Traffic • Set up of work site (November 2017) • Removal of roadway median; existing bridge is split into two parallel bridge spans. A temporary barrier is installed between the spans. • Southern span (northbound lanes) is removed. • Traffic is reduced to one lane per direction across Carlin Springs Road bridge • When south span is removed, all traffic on Carlin Springs and George Mason must be rerouted via detours (December 1-3 weekend)

Detours - Used Only During Short Term Closures

Phase 2 Work & Maintenance of Traffic • Construction of new south side bridge section • All traffic (vehicles and pedestrians) is shifted to the north span • When steel beams are installed both roads will be closed for one day (a Saturday, date TBD)

Phase 3 Work & Maintenance of Traffic • Removal of existing north side span • Construction of new north side bridge span • Construction of new sewer line in Carlin Springs Rd and Abingdon Street. • All traffic (vehicles and pedestrians) is shifted onto the new south side span. • When north span is removed, all traffic on Carlin Springs & George Mason Drive must be rerouted via detours (a weekend in early summer 2018), Also closure on one Saturday for steel beams installation. • Abington Street within sewer line construction zone is reduced to one lane (north bound only).

Sewer Line Construction

Phase 4 Work & Maintenance of Traffic • Refurbishment of bridge abutments and wing walls • Completion of permanent sidewalks on new bridge • Vehicular traffic on Carlin Springs Road will be returned to two lanes in each direction across bridge • Full pedestrian travel (both sides of bridge) will be restored after permanent sidewalks are completed

Completion • Removal of construction trailer, temporary signage and building materials • Restoration of site and planting of new landscaping

• No impacts on traffic movement (vehicles or pedestrians)

Expected Community Concerns • Cut-through traffic as a result of short-term lane closures and traffic detours • Potential traffic congestion from lane reductions & detours during construction • Some access restriction on N. Abingdon Street • Pedestrian crossings of N. Carlin Springs Road at N. Wakefield and N. Edison streets • Rerouting or disruptions to Metrobus Route 25 service • Noise & dust from demolition and construction

Contacts: Web page: www.arlingtonva.us/projects/carlin-springs-road-bridge/ • Arlington’s Bridge Engineer – Ravinder Singh, 703 228-3661, [email protected] • Arlington’s Construction Manager – TBD, will be posted on webpage • Rustler Construction’s Site Manager -

Landscaping – Tree Removal, Replacement & Protection