Submittal #03 2000-9.0 03 2000 - CONCRETE REINFORCING

Report 6 Downloads 61 Views
Submittal #03 2000-9.0 03 2000 - CONCRETE REINFORCING Project: 15060018 - Boulder Commons 2440 Junction Place Boulder, Colorado 80301

Mortenson Construction 1621 Eighteenth Street Suite 400 Denver, Colorado 80202 Phone: (303) 295-2511  Fax: (303) 297-8055

South Building, Pier Caps, Pilasters, Grade Beams, SOG, SPEC SECTION:

03 2000 - CONCRETE REINFORCING 

CREATED BY:

Barbara Waggoner(Gerdau Reinforcing Steel)

STATUS: 

Open

DATE CREATED:

06/03/2016 

ISSUE DATE:

// 

REVISION:

0

RESPONSIBLE CONTRACTOR:

Gerdau Reinforcing Steel

RECEIVED FROM:

Barbara Waggoner

RECEIVED DATE:   //

SUBMIT BY: 

// 

FINAL DUE DATE: 07/01/2016

LOCATION: 

 

TYPE:

Shop Drawings

COST CODE: 

APPROVERS:

Jose Nieto (Mortenson Construction - Denver), Jose Nieto (Mortenson Construction - Denver), Will Faber (Coburn)

BALL IN COURT: Will Faber (Coburn) DISTRIBUTION: Barbara Waggoner (Gerdau Reinforcing Steel), Ella Pilgrim (Mortenson Construction - Denver), John McCorkle (Mortenson Construction Denver), Seki Kofe (Mortenson Construction - Denver), Ted Godfrey (Studio NYL Structural Engineers), Will Faber (Coburn) , Shannon Brookins (Coburn), Jose Nieto (Mortenson Construction - Denver), Mike MaGuire (Mortenson Construction - Denver) DESCRIPTION: Please see the attached submittals for approval.  Please review and advise if you have any questions.     Thank you,   Barb ATTACHMENTS: BOULDER COMMONS SOUTH BLDG PIER CAPS PILASTERS GR BMS SOG FOR APPROVAL (2).pdf

  SUBMITTAL WORKFLOW #

NAME

SUBMITTER/ APPROVER

SENT DATE

DUE DATE

RETURNED RESPONSE DATE

Forwarded For Review



Jose Nieto

Approver 

6/9/2016

7/1/2016



Will Faber

Approver 

6/9/2016

6/23/2016

Pending



Jose Nieto

Approver 

7/1/2016

Pending

6/9/2016

ATTACHMENTS

COMMENTS

03 200-SD-09-S BLDG PIER CAPS Please see PILASTERS GR attached. BMS SOG.pdf 

   

BY

Mortenson Construction

DATE

COPIES TO

Page 1 of 1

Printed On: 06/09/2016 04:03 PM

'U' bars top an bottom per RFI 80 response.SNYL

'U' bars top an bottom per RFI 80 response.SNYL

'U' bars top an bottom per RFI 80 response.SNYL 'U' bars top an bottom per RFI 80 response.SNYL

'U' bars top an bottom per RFI 80 response.SNYL

'U' bars top an bottom per RFI 80 response.SNYL

'U' bars top an bottom per RFI 80 response.SNYL

'U' bars top an bottom per RFI 80 response.SNYL

'U' bars top an bottom per RFI 80 response.SNYL 'U' bars top an bottom per RFI 80 response.SNYL 'U' bars top an bottom per RFI 80 response.SNYL 'U' bars top an bottom per RFI 80 response.SNYL

'U' bars top an bottom per RFI 80 response.SNYL

'U' bars top an bottom per RFI 80 response.SNYL

T.GODFREY -STUDIO NYL

'U' bars top an bottom per RFI 80 response.SNYL

'U' bars top an bottom per RFI 80 response.SNYL

'U' bars top an bottom per RFI 80 response.SNYL

06/23/2016

'U' bars top an bottom per RFI 80 response.SNYL GC shall coordinate these submittal shop drawings with all current architectural and structural construction documents and all pertinent ASI's and RFI's, and previously submitted shop drawings. Verify all dimensions and elevations with architectural plans.- SNYL

'U' bars top an bottom per RFI 80 response.SNYL

Yes, structural construction documents are the correct basis for shop drawings.- SNYL

'U' bars top an bottom per RFI 80 response.SNYL

Lap location shall be in compliance with general notes, S000-B.- SNYL

T.GODFREY -STUDIO NYL

06/23/2016

GC shall coordinate these submittal shop drawings with all current architectural and structural construction documents and all pertinent ASI's and RFI's, and previously submitted shop drawings. Verify all dimensions and elevations with architectural plans.- SNYL

T.GODFREY -STUDIO NYL

06/23/2016

GC shall coordinate these submittal shop drawings with all current architectural and structural construction documents and all pertinent ASI's and RFI's, and previously submitted shop drawings. Verify all dimensions and elevations with architectural plans.- SNYL