Weekly Report #010 Week Ending 9/25/15
Prepared By Zach Watson Ryan Kirlin Brian Semerad
NGC Group, Inc. NGC Group, Inc. NGC Group, Inc.
[email protected] [email protected] [email protected] Schedule: Project Commencement Date: Weather Delays This Week: Other Delays This Week:
05/18/15 3 Day 0 Days
Substantial Completion Date: Total Weather Delays to Date: Total Other Delays to Date:
The following items were completed during the weeks of September 21, 2015: • • • •
Table Rock is laying stone on the exterior. Frank Bevins is painting the awnings. Silver Ridge continued to pour the parking lot. Electrical Enterprises ran conduit to the transformer.
The following items are scheduled for the week of September 28, 2015: • • •
Silver Ridge will continue to pour exterior concrete. Lynch will start exterior siding. Table Rock will continue to lay stone.
Critical Items, RFI’s, & Submittals:
10/16/15 10 Days 0 Days
Progress Pictures
Figure 1: South Elevation
Figure 2: Parking Lot
Figure 3: Exterior Stone
Figure 4: Exterior Stone
Figure 5: Exterior Stone
Figure 6: Exterior Stone
Distribution List Name
Company
Email
Mike Marsh Alan Schmidt Jim Hutchinson Jackson Friesen Zach Watson Ryan Kirlin Sarah Larkin Wendy Stork Justin Hernandez Chris Heese Ray Norkiewicz
Realty Trust Group Hutchinson Architect’s, P.C. Hutchinson Architect’s, P.C. NGC Group, Inc. NGC Group, Inc. NGC Group, Inc. NGC Group, Inc. NGC Group, Inc. NGC Group, Inc. NGC Group Inc NGC Group, Inc.
[email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected]