MassDOT State Report

Report 0 Downloads 63 Views
MassDOT State Report

Northeast Pavement Preservation Partnership Portland, ME May 9, 2017

EDC-4

2

10/10/2017

EDC-4 Pavement Preservation (When, Where, and How) Develop MassDOT pavement preservation policy/program (objectives, funding, roles, & treatment scope). Prepare & issue PP Communication Plan. Explore dedicated CIP/STIP funding item for PP treatments. Assist & inform in updating Healthy Transportation Policy (HTP) criteria applicable to PP treatment projects. Identify at least 5 candidate 2019 PP projects in Districts. Engage Local Agencies on use of PP as “whole-life” investment and standard business practice.

3

10/10/2017

Example Projects & Treatments I-495 Franklin-Foxboro (UTBO/Fog Seal/HVSB) Route 31 Dudley (HIP) I-91 Longmeadow Springfield (UTBO/Fog Seal) I-291 Springfield Chicopee (UTBO/Fog Seal) Route 2 Lexington-Cambridge(UTBO/Fog Seal) Route 146 Uxbridge Millville(UTBO/Fog Seal) Route 7 Stockbridge-Lenox-Lee (Cape Seal/HiPTO) I-290 Auburn (Micromill & OGFC with Spray Paver I-195 Dartmouth-New Bedford (Micromill & OGFC with Spray Paver Route 5 West Springfield-Holyoke (CPR)

4

10/10/2017

I-495 Foxboro Wrentham Plainville Pavement Preservation and “Related Work” • 10 CL Miles ~ 6 lanes + 2 Shoulders • High Velocity Shotblasting & Fog Seal NB • UTBO SB Mainline & Fog Seal Shoulder • 14 Bridges with SSC-W for deck preservation • New Modified Strip Seal Joints • Stormwater/Environmental Work

Project Duration – 300 DAYS

Pavement, Bridge Decks & Water Quality Office Estimate = $5.6M Low Bid $6.9M • UTBO, Fog Seal, Striping, Etc. = $3.4M • Stormwater/Environmental = $1.4M • Bridge Deck Preservation = $740K • “Maintenance” (Clearing/Grubbing, Tree Trimming, Drain/pipe cleaning) = $300K • Traffic Control = $1.1M

Why? 10-12 Days UTBO Paving Mainline 20-25? Days Fog Sealing 10-15? Days Striping 30-40? Days Bridge Paving

Project Duration = 300 DAYS Traffic Control Item $2500/day

Bids higher than expected Project duration and extensive stormwater likely contributed to higher costs.

I-495NB Wrentham- OGFC

8

10/10/2017

I-495SB Wrentham- HMA

9

10/10/2017

10

10/10/2017

Bridge Deck Preservation

11

10/10/2017

I-495NB Friction Testing

12

10/10/2017

| Leading the Nation in Transportation Excellence | www.mass.gov/massdot

13

10/10/2017

Successes and Challenges Successes ARGG Mixtures – 9 years and counting! Getting Pavement Preservation Projects out! Using new treatments!

Challenges Staffing Scope Creep 5 Year Preservation Project Initiation Period HTP and Issues identified in EDC-4. 14

10/10/2017

Thank You Edmund Naras Pavement Management Engineer MassDOT-Highway Division (857) 368-8989 [email protected]