RENOVATION & REFURBISHMENT UPDATE Country: Thailand

Location: Hua Hin

Hotel Name: YaiYa Resort

Today’s Date: 13 January 2014

Contact Name for Building Work: Ms. Krisana Kalapagdee / Junior Director of Sales

Contact Email: [email protected]

Is there any refurbishment, renovation or building work planned at the Hotel during this year or next year?: No

Adjacent or nearby the hotel?: Yes

Date of Commencement: 15 January 2014

Date of Completion: 31 October 2016

(Specify estimated dates if not yet finalised)

Description of the renovation work:- (e.g. upgrading of pool, refurbishment of restaurant etc): Due to the construction of the neighbor\\'s project beside YaiYa Resort will be started on the 15th of January 2014 and expected to complete before October 2016. The fences have been already installed to minimize direct optical disturbance and dampen noise.

What does the work involve? (e.g. - drilling, hammering, painting, scaffolding etc):

Hours and days of the week that the work will be carried out: Hours: 09:00 am - 06:00 pm

Days of the week: Daily

How will the renovation affect main service areas (pool, lobby, restaurants, bars, beach, etc):

What is the extent of disturbance to guests (i.e. noise and dust, visual etc) and what is being done to minimise the impact?: Construction is underway at a neighboring and there may be noise disturbance from the construction work. What facilities/services will not be available/limited to guests during the renovation?:

Are there are any arrangements to provide these services in another part of the Report (or at another Resort?):

Can you guarantee rooms for Exotissimo clients gusets away from the renovation area?: