The Edge - (160901) - Aggregate

Report 10 Downloads 32 Views
N. California S. California Washington Colorado

Submittal The Edge Milpitas Aggregate Palisade Builders, Inc. 1875 South Bascom Avenue, Suite 2400 Campbell, CA 95008 Dean Guerrero, Assistant Project Manager t 408-429-7701

PALISADE BUILDERS, INC General Contractors CA Lic. 569716

NO EXCEPTIONS TAKEN

DG

MAKE CORRECTIONS NOTED REVISE AND RESUBMIT REJECTED SUBMIT SPECIFIED ITEM CORRECTIONS OR COMMENTS MADE RELATIVE TO SUBMITTALS DURING THIS REVIEW DO NOT RELIEVE THE SUBCONTRACTOR FROM COMPLIANCE WITH THE REQUIREMENTS THE DRAWINGS AND SPECIFICATIONS. THIS CHECK IS ONLY FOR REVIEW OF GENERAL CONFORMANCE WITH THE DESIGN CONCEPT OF THE PROJECT AND GENERAL COMPIANCE WITH THE INFORMATION GIVEN IN THE CONTRACT DOCUMENTS. THE SUBCONTRACTOR IS RESOINSIBLE FOR CONFIRMING AND CORRELATING ALL QUANTITIES AND DIMENSIONS; SELECTING FABRICATION PROCESSES AND TECHIQUES OF CONSTRUCTION; COORDINATING HIS/HER WORK WITH THAT OF OTHER TRADES; AND PERFORMING HIS/HER WORK IN A SAFE, TIMELY, AND SATISFACTORY MANNER.

SUBMITTAL NO.

017.0 03 00 00 Aggregate - Garage Foundation Bedding (Specification): Conco

Sheree Moreno - Sep 1, 2016 Gonsalves & Santucci, Inc. d.b.a. Conco

The Conco Companies

◦ 5141 Commercial Circle - Concord, CA 94520 ◦ 925-681-6650 ◦ ConcoNow.com ◦ Lic. 199902

The Conco Companies

Submittal Items Aggregate!.....................................................................................................................................................1 Product: 3/4” X 1/2” Crushed Rock from Desilva Gates, Sunol Location: Foundation bottoms as directed by Soils Engineer

Aggregate!.....................................................................................................................................................2 Product: Class 2 AB from Graniterock at Graniterock Way, San Jose Location: Directly over pads

Aggregate!.....................................................................................................................................................3 Product: Class 2 AB from Stevens Creek Quarry, Sunnyvale Location: Directly over pads

Submittal List

i

Product Specification

Aggregate Product: 3/4” X 1/2” Crushed Rock from Desilva Gates, Sunol Location: Foundation bottoms as directed by Soils Engineer

PROJECT REQUIREMENTS

The Conco Companies

1

Product Specification

Aggregate Product: Class 2 AB from Graniterock at Graniterock Way, San Jose Location: Directly over pads

PROJECT REQUIREMENTS

The Conco Companies

2

Baldrige Award Winner Research-Technical Services Ph. (831) 768-2330 FAX (831) 768-2403

350 Technology Drive; Watsonville, CA 95076

Capitol Recycle Material Certification San Jose, CA Product: ¾” (19mm) Class II Baserock (#033)

Date: August 26, 2016

Contractor: Conco Cement Project: The Edge Milpitas Graniterock conducts regular sampling and testing of its materials, in accordance with ASTM or other applicable standards. The results listed below are average results derived from these tests. Based on the testing conducted, Graniterock certifies that the material identified on this certificate typically has the following physical properties: ! Gradation: Cumulative Percent Passing Sieve Sizes Inches mm/um 1.0 25.4mm ¾” 19 mm #4 4.75 mm # 30 600 um # 200 75 um Sand Equivalent: R- Value : Durability Index:

Capitol Cl.II Base 100 96 48 19 6.2 53 80 64

Caltrans Section 26 100 90-100 35-60 10-30 2-9 25 min. 78 min. 35 min.

Submitted by:

Greg Wilkinson RTS Aggregates Manager, LEED AP BD+C Research Technical Services

Product Specification

Aggregate Product: Class 2 AB from Stevens Creek Quarry, Sunnyvale Location: Directly over pads

PROJECT REQUIREMENTS

The Conco Companies

3

Dean Guerrero From: Sent: To: Cc: Subject:

Sheree Moreno <[email protected]> Thursday, September 01, 2016 1:28 PM Blade, Greg; Dean Guerrero Eric Carbajal; Stephen Wilson RE: The Edge - (160830) - Concrete (Readymix)

All‐   Locations for rock will be as follows:     ¾” Crushed rock will be at footing/foundation bottoms.  Class 2 AB will be placed directly over pads, under slab‐on‐grade.   Please give me a call if there are any further questions or comments.   Thank you,   Sheree Moreno Gonsalves & Santucci, Inc. dba Conco and Conco Pumping 5141 Commercial Circle Concord, CA 94520 [email protected] Phone 925‐681‐6634 Fax 925‐681‐6504  www.Conconow.com     From: Sheree Moreno   Sent: Thursday, September 01, 2016 11:43 AM  To: 'Blade, Greg' ; Chad Watson   Cc: Dean Guerrero ; Eric Carbajal <[email protected]>; Stephen Wilson  <[email protected]>  Subject: RE: The Edge ‐ (160830) ‐ Concrete (Readymix) Good Morning Greg + Dean,   Please see attached our rock submittal. Please reply confirming receipt.   Thank you,   Sheree Moreno Gonsalves & Santucci, Inc. dba Conco and Conco Pumping 5141 Commercial Circle Concord, CA 94520 [email protected] Phone 925‐681‐6634 1

Fax 925‐681‐6504  www.Conconow.com       From: Blade, Greg [mailto:[email protected]]   Sent: Tuesday, August 30, 2016 8:09 AM  To: Chad Watson   Cc: Dean Guerrero ; Sheree Moreno <[email protected]>; Eric Carbajal  <[email protected]>; Stephen Wilson <[email protected]>  Subject: Re: The Edge ‐ (160830) ‐ Concrete (Readymix)

Chad Send rock submittal his morning. Greg Blade Sent from my iPhone On Aug 30, 2016, at 7:46 AM, Chad Watson wrote: Good Morning Dean, See attached. Once approved this will be the mix we order for tomorrow’s shoot. Please reply confirming a successful download. https://www.dropbox.com/s/ikf3ojft3o2bszk/The%20Edge%20-%20%28160830%29%20%20Concrete%20%28Readymix%29.pdf?dl=0 Kind Regards, Chad M. Watson [email protected] Gonsalves & Santucci Inc., dba Conco 5141 Commercial Circle Concord, CA 94520 www.ConcoNow.com 925-681-6650 925-260-3433 TEAM = Together Everyone Achieves More On Aug 30, 2016, at 7:25 AM, Dean Guerrero wrote: Chad/Sheree,   2

Our backs are against the wall now for this 6,000psi Shotcrete Mix Design for Sheer  Walls and the scheduled Nozzleman test tomorrow! Send the mix design NOW, because  we still need it reviewed/approved….  

Dean Guerrero Assistant Project Manager Palisade Builders, Inc. 510‐648‐8094 Cell Email: [email protected] The Edge Project 765 Montague Expressway Milpitas, CA 95035   1875 S. Bascom Ave., Ste. 2400 Campbell, CA. 95008 (408) 429‐7700 Main Office (408) 429‐7701 Office Fax  

      From: Dean Guerrero (Palisade Builders, Inc.) [mailto:[email protected]] Sent: Monday, August 29, 2016 12:06 PM To: Dean Guerrero Subject: FW: Submittals: #013.0: 03 30 00 Concrete Design Mix (Readymix)

The Edge

More details: View online |

View PDF

From:

Dean Guerrero (Palisade Builders, Inc.)

Date:

Monday, August 29, 2016 at 12:05 pm PDT

Sent To:

Sheree Moreno (Conco Company) Chad Watson (Conco Company)

CC:

Eric Carbajal (Palisade Builders, Inc.) Stephen Wilson (Palisade Builders, Inc.) Greg Blade (Palisade Builders, Inc.) Dean Guerrero (Palisade Builders, Inc.)

Attachments:

None

3

URGENT!!!!!

All mix designs submitted have been approved, but apparently there is ALSO a requirement for 6,000psi design mix for some shotcrete shear walls called for in some elevations; please IMMEDIATELY forward that design mix ASAP!!!

Dean Guerrero Assistant Project Manager Palisade Builders, Inc. 510-648-8094 Cell Email: [email protected]

The Edge Project

Sent From Procore.

Submittal Item Details Project:

The Edge

Spec Section:

03 30 00 - Cast-in-Place Concrete

Submittal #:

013.0

Title:

03 30 00 Concrete Design Mix (Readymix)

Cost Code:

3 - DIV 3 - CONCRETE

Type:

Specification

Responsible Contractor:

Conco Company

Received From:

Sheree Moreno

Ball In Court:

Caroline Vedder

Approvers:

Bane, Chris (FBA Inc.) Vedder, Caroline (FBA Inc.)

Confirmed Delivery Date:

08/26/16

Actual Delivery Date:

08/26/16

4

Final Due Date:

08/30/16

Description:

URGENT - please EXPEDITE the review/approval of the attached submittal for the Garage Structural Concrete Mix designs.

Your expedited response is needed to avoid production delays, due to the late receipt of the mix design from trade partner.

Dean Guerrero Palisade Builders Inc.

08/29/2016 I deleted the original attachment that was sent out on 08/26/2016, and have replaced the attachment with the COMPLETE submittal package just received at 09:44am this morning. Please EXPEDITE this submittal as the Nozzlemen testing is schedule for this Wednesday (08/31/2016). Attachments:

The Edge - (160825) - Concrete (Readymix)_160829.pdf

Approver:

Chris Bane

Date:

Sent: 08/29/16 Due: 08/30/16 Returned: 08/29/16

Response:

Approved As Noted

Attachments:

The Edge - (160825) - Concrete (Readymix).pdf

Comments:

Please submit a 6000 psi mix for the shear walls. See shear wall elevations.

Approver:

Caroline Vedder

Date:

Sent: 08/29/16 Due: 08/30/16 Returned:

Response:

Pending

5

Attachments:

None

Comments:

None

More details: View online |

View PDF

Powered by Procore | [email protected] | http://support.procore.com