water transmission main - KC Water Services

Report 4 Downloads 121 Views
INVESTING

PUBLIC MEETING Why: Water Transmission Main Project When: Tuesday, June 7, 2016 7:00 p.m.

Englewood Rd

54th St

N. Oak Trfwy

Arrowhead Transmission Main Phase 3 - N. Oak Trfwy to Hwy 169

PROJECT AREA

Hwy 169

WATER TRANSMISSION MAIN

IN

Where: Harmony Vineyard Church 600 NE 46th St. Kansas City, MO 64116

Construction Occurring June 2016 to May 2017

YOUR INVESTMENTS AT WORK

WATER TRANSMISSION MAIN Arrowhead Tranmission Main Phase 3 - N. Oak Trfwy - Hwy 169 WHAT? • Important infrastructure work will be

performed in your neighborhood.

WHO? • Kissick Construction, and Black &

Veatch in partnership with KC Water.

• Water transmission main extension.

WHERE?

WHY? • The new water transmission main is

necessary to increase the amount of water supplied to the North Booster System including Arrowhead Pump Station.

The transmission main alignment runs along N Oak Trafficway to NE 54th Street to the west ending at NE Englewood Rd and Hwy 169.

IMPROVEMENTS? • Increased system reliability • Increased capacity for north system.

WHAT TO EXPECT? • Survey crews will be in the area and

clearly identified.

• Large equipment will be used, creating

noise and dusty conditions - we will work to minimize this inconvenience.

• Temporary lane closures and detours

will occur.

WHEN? • Construction begins June 2016 • Field investigations and design are

complete

• Curbs, sidewalks, and streets affected

by construction will be restored.

• Lawn and wooded areas will be

restored once work is complete.

QUESTIONS? Specific questions about this project can be directed to: • Kelly Finn, Project Manager,

KC Water at 816-513-0351 or [email protected]

• Matt Rothermel, Project Manager,

Kissick at 816-363-5530 or [email protected]