INVESTING INFLOW AND INFILTRATION REDUCTION

IN

PROJECT AREA

Blue River Central Area 2 Project

Field Crews Working May 2015- September 2015

YOUR INVESTMENTS AT WORK

INFILTRATION AND INFLOW REDUCTION Blue River Central Area 2 Project WHO?

WHAT? • Important field investigations of the sanitary collection system in your area.

WHAT TO EXPECT?

• Kansas City Water Services assisted

• Various field crews inspecting

by CDM Smith, Parson and Associates, SK Design Group, Taliaferro & Browne, and TREKK Design Group.

manholes and cleaning the public sewer lines.

• Smoke from smoke testing activities.

WHY? • Investigate the existing sewers to determine locations of needed sewer repairs.

• Reduce risk and frequency of sanitary overflows and basement backups.

WHERE?

• Temporary street closures.

The project is located in Kansas City, Missouri within the following boundaries:

• Public meeting will be held to

• Northern boundary: Sni-A-Bar Road • Southern boundary: 67th Street

• Rehabilitate the aging sewer system.

• Eastern boundary: Blue Ridge Cutoff

• Meet regulatory requirements as part

• Western boundary: Blue River

of KC’s Overflow Control Program.

• Field investigations will be ongoing May 2015 through September 2015.

• Design professional services will be conducted from February 2016 through May 2016.

• Construction will occur between September 2016 to December 2017.

• Crews may knock on your door if they need to inspect the sewer or manholes on your property.

• Crews will not ask to enter your

IMPROVEMENTS?

WHEN?

inform property owners about the field investigations and project schedule.

home or building.

• Current activity includes identifying needed sewer rehabilitation repairs.

CONTRACT AMOUNT Design professional services contract includes all services rendered through the construction phase of the project.

• $655,000

QUESTIONS? Specific questions about this project can be directed to: • Priya Iyengar, Project Manager,

KC Water Services, 816-513-0579 or [email protected] • Lisa Brink, Project Manager,

CDM Smith, 816-412-3109 or [email protected] • Ed Eiler, Field Crew Coordinator,

www.kcwaterservices.org

TREKK Design Group, 913-230-8694 or [email protected]