crrma board presentation 2013 el paso cmp - recent

Report 1 Downloads 25 Views
CRRMA BOARD PRESENTATION 2013 EL PASO CMP RECENT CHANGE ORDERS Edgar E. Fino, P.E. March 19, 2018

Camino Real Regional Mobility Authority CRRMA CHANGE ORDERS A CRRMA Board Resolution dated February 14, 2018 authorized the Executive Director to approve individual construction change orders in amounts up to and including $100,000 without prior Board approval; provided that a report is provided to the Board at the next meeting on any such approvals granted. The information on the following slides identify the change orders for two El Paso County Comprehensive Mobility Plan projects that were approved pursuant to the referenced Board Resolution. 2

Eastlake Phase 2

3

Eastlake Phase 2 CO

Description

Cost

Status

#1

Bore 6” conduit to connect to water meter.

$7,200.00

Approved

#2

Cut sharp edges of landscape sculpture.

$1,890.00

Approved

#3

Modify curb inlet B-11 to a surface grate inlet due to a conflict with an existing water line.

$12,986.65

Approved

#4

Construction of new retaining wall needed around Pond #6 within the Phase V limits of the projects due to an issue with elevations.

$113,022.87

Approved

#5

Reduction in price of desert willow trees due to availability of tree caliper size for landscaping.

-$4,350.00

Approved

#6

EPEC to furnish/install 4 transformers for illumination.

$9,453.15

Approved

#7

Remove existing trees in conflict w/ proposed work.

$3,250.00

Approved

4

Eastlake Phase 2 CO

Description

Cost

Status

#8

EPEC to furnish/install 2 transformers for Traffic Signals.

$10,825.59

Approved

#9

Storm sewer pipe quantity adjustment due to an error on the plans.

$22,516.00

Approved

$68,295.99

Approved

#10 Over excavation of Pond #1 due to layer of clay found at the bottom elevation of the pond. Total CO Approved

$245,090.25

Total Project Bid Cost $13,464,149.00 Total CO / Total Project Bid Cost

1.82%

5

Vista Del Sol Drive

6

Vista Del Sol Drive CO

Description

Cost

Status

#1

(PSB) Material cost impacts due to project start delays and storms (Hurricanes).

$29,229.48

Approved

#2

(EP County) Material cost impacts due to project start delays and storms (Hurricanes).

$3,414.46

Approved

#3

(EP County) Repair existing potholes on Cherrington St.

$12,720.00

Approved

#4

(PSB) Sanitary sewer tie-in connection design conflict with existing manhole.

$24,423.50

Approved

Total CO Approved

$69,787.44

Total Project Bid Cost $4,582,190.00 Total CO / Total Project Bid Cost

1.52% 7

Questions?

Camino Real Regional Mobility Authority 801 Texas Avenue El Paso, Texas 79901 (915) 212-1072 [email protected] www.crrma.org

8