Innovative Contracting Practices for Bridge Preservation

Report 1 Downloads 89 Views
Innovative Contracting Practices for Bridge Preservation Jeremy Hunter, INDOT Bridge Design Manager

Why Pursue Innovative Contracting? 

Time Gap (Capital Program) 



Skills Gap (Maintenance Program) 



Developing contracts takes time and added resources.

Special skills, techniques, or labor is needed to deploy repairs.

Equipment Gap (Maintenance Program) 

Specialized equipment, large work quantities

Slide 2

INDOT IDIQ Program 

Why IDIQ? 

Expedites Construction Procurement.



Competitively bid



Reduces overhead costs / contract administration time 





Single Contract Procurement

Contractor provides “on call” construction services from concept to close-out for a wide variety of infrastructure needs. Eligible for Federal Funding

Slide 3

INDOT IDIQ Program 

Contract under which INDOT may assign contractors an ongoing series of individual job orders 

Pre-priced task catalog  



Joint-Scope Meetings



Tailors the project to the need Reduces contractor risk Ensures a collaborative partnership



Collaboration Improves Work Zone Safety

 



Competitively bid overhead and profit factors Comprehensive task items

On-Call Contract Functionality 

Enables quick response to preservation needs

Slide 4

INDOT IDIQ Program 

Two Contracts Per District: 

Bridge Preservation   



Pavement Preservation  

  

Beam Support and Repair Substructure Repairs Expansion Joint Repairs / Replacement Asphalt and Concrete Pavement Patching Micro-Surfacing

First letting (complete): Feb. 17, 2016 INDOT and Contractor opted to renew both contracts for 2017 Rockville Road over I-465

Slide 5

INDOT IDIQ Program 

Rockville Road over I-465: Bridge Hit

Slide 6

INDOT IDIQ Program

Questions? Jeremy Hunter, PE INDOT Bridge Design and Load Rating Manager [email protected]