Dilley ISD 2015 Bond AWS

Report 0 Downloads 102 Views
Dilley ISD 2015 Bond

10/13/2016

July 18, 2016 Update

1

Completed Tasks

Dilley ISD - 2015 Bond

Approved Champion Environmental Services for the asbestos consultant for abatement on the project (1/18/2016) All construction partners have access through Krueger’s ProCore system for monitoring project (1/18/2016) Selected A/C for elementary gym (3/9/2016) 10/13/2016

2

Completed Tasks

Dilley ISD - 2015 Bond

DD set documents approved – March 10th Project sent out for advertisement – April 21st

Final CDs of the project completed – April 21st 10/13/2016

3

Completed Tasks

Dilley ISD - 2015 Bond

Selected asbestos contractor for removal May 10th – Camacho Demolition for $21,780 Held pre-bid mtg – May 16th @ 10:00am Permit approved with the city – May 16th board meeting 10/13/2016

4

Completed Tasks

Dilley ISD - 2015 Bond

 Approved GMP of $ 11,847,223 at the June 1st board meeting  Krueger received keys for buildings as needed (June 14th)

Pre-construction mtg held – June 16th

10/13/2016

5

Completed Tasks

Dilley ISD - 2015 Bond

 Asbestos abatement has been completed (June 27th)  Building and site demo almost complete at the football stadium

10/13/2016

6

Completed Tasks

Dilley ISD - 2015 Bond

 Krueger has set up their work area in the old HS 

10/13/2016

7

On-Going Tasks

Dilley ISD - 2015 Bond

 Demo at the old High School  Completing all disconnects as needed  Complete the parking lot at the PK-2 end of elementary

10/13/2016

8

Upcoming Tasks

Dilley ISD - 2015 Bond

Need to receive revised schedule (from Krueger) Demo of CTE building  Temporary fencing will go up around the construction areas – (fully set up)

10/13/2016

9

Upcoming Tasks

Dilley ISD - 2015 Bond

 Change order in contract for the asphalt at HS (???) – to be credited Elem A/C scheduled for delivery – July 18th

 Demo for the 3rd/4th grade building and the PE/maint building upcoming 10/13/2016

10