Approved Champion Environmental Services for the asbestos consultant for abatement on the project (1/18/2016) All construction partners have access through Krueger’s ProCore system for monitoring project (1/18/2016) Selected A/C for elementary gym (3/9/2016) 10/13/2016
2
Completed Tasks
Dilley ISD - 2015 Bond
DD set documents approved – March 10th Project sent out for advertisement – April 21st
Final CDs of the project completed – April 21st 10/13/2016
3
Completed Tasks
Dilley ISD - 2015 Bond
Selected asbestos contractor for removal May 10th – Camacho Demolition for $21,780 Held pre-bid mtg – May 16th @ 10:00am Permit approved with the city – May 16th board meeting 10/13/2016
4
Completed Tasks
Dilley ISD - 2015 Bond
Approved GMP of $ 11,847,223 at the June 1st board meeting Krueger received keys for buildings as needed (June 14th)
Pre-construction mtg held – June 16th
10/13/2016
5
Completed Tasks
Dilley ISD - 2015 Bond
Asbestos abatement has been completed (June 27th) Building and site demo almost complete at the football stadium
10/13/2016
6
Completed Tasks
Dilley ISD - 2015 Bond
Krueger has set up their work area in the old HS
10/13/2016
7
On-Going Tasks
Dilley ISD - 2015 Bond
Demo at the old High School Completing all disconnects as needed Complete the parking lot at the PK-2 end of elementary
10/13/2016
8
Upcoming Tasks
Dilley ISD - 2015 Bond
Need to receive revised schedule (from Krueger) Demo of CTE building Temporary fencing will go up around the construction areas – (fully set up)
10/13/2016
9
Upcoming Tasks
Dilley ISD - 2015 Bond
Change order in contract for the asphalt at HS (???) – to be credited Elem A/C scheduled for delivery – July 18th
Demo for the 3rd/4th grade building and the PE/maint building upcoming 10/13/2016