Dilley ISD 2015 Bond

Report 3 Downloads 190 Views
Dilley ISD 2015 Bond

5/10/2016

May 16, 2016 Update

1

Dilley ISD - 2015 Bond

Project Process

Concept

5/10/2016

Schematic

Design

TM

Bidding

Construction

2

Completed Tasks

Dilley ISD - 2015 Bond

BWA Amendment for 2015 Bond Sledge Program Management Assistance Agreement Executed 09/21/15 Sledge provided ISD access to Basecamp (Project Management Tool) 09/22/15 CMR Selection Completed 10/26/15 Bond Passed 11/03/15 Schematic Design Approved By Board 12/14/15 5/10/2016

3

Completed Tasks

Dilley ISD - 2015 Bond

Approved Champion Environmental Services for the asbestos consultant for abatement on the project (1/18/2016) All construction partners have access through Krueger’s ProCore system for monitoring project (1/18/2016) Selected A/C for elementary gym (3/9/2016) 5/10/2016

4

Completed Tasks

Dilley ISD - 2015 Bond

DD set documents approved – March 10th Project sent out for advertisement – April 21st

Final CDs of the project completed – April 21st 5/10/2016

5

Completed Tasks

Dilley ISD - 2015 Bond

Selected asbestos contractor for removal May 10th – Camacho Demolition for $21,780 Held pre-bid mtg – May 16th @ 10:00am

5/10/2016

6

Upcoming Tasks

Dilley ISD - 2015 Bond

Will continue to revise schedule (from Krueger & BWA) Approve the permit with the city – May 16th (tonight’s agenda) Bids are due – May 24th (Krueger) Approve GMP – June 1st (DISD Board) 5/10/2016

7

Upcoming Tasks

Dilley ISD - 2015 Bond

Begin asbestos abatement – early June First day construction work can begin – June 15th (Krueger)

5/10/2016

8