BWA Amendment for 2015 Bond Sledge Program Management Assistance Agreement Executed 09/21/15 Sledge provided ISD access to Basecamp (Project Management Tool) 09/22/15 CMR Selection Completed 10/26/15 Bond Passed 11/03/15 Schematic Design Approved By Board 12/14/15 3/7/2016
3
Completed Tasks
Dilley ISD - 2015 Bond
Approved Champion Environmental Services for the asbestos consultant for abatement on the project (1/18/2016) All construction partners have access through Krueger’s ProCore system for monitoring project (1/18/2016) Selected A/C for elementary gym (3/9/2016) 3/7/2016
4
Upcoming Tasks
Dilley ISD - 2015 Bond
Design Development On-going (by BWA) – Approve March 10th Begin Work on Construction Documents – (by BWA)
Will continue to revise schedule (from Krueger & BWA) 3/7/2016
5
Upcoming Tasks
Dilley ISD - 2015 Bond
Continue to develop preliminary budget (from Krueger & Sledge) Approve asbestos abatement firm for the 2015 Bond Program Send project out for bid – End of April/First of May Approve GMP – End of May 3/7/2016