HYDRO INSTALLATIONS

SIMON DENNIS – RENEWABLES FIRST LTD RENEWABLE ENERGY MARKET PLACE, WESTPOINT CENTRE, 19 MARCH 2013

THE HYDROPOWER PROCESS: 5 STAGES FEASIBILITY: PRE-FEASIBILITY & FEASIBILITY STUDIES PERMISSIONS: ABSTRACTION AND / OR IMPOUNDMENT LICENCES (ENVIRONMENT AGENCY, NATURAL RESOURCES WALES OR SCOTTISH ENVIRONMENTAL PROTECTION AGENCY); FLOOD DEFENCE CONSENT (ENVIRONMENT AGENCY, NATURAL RESOURCES WALES, SCOTTISH ENVIRONMENTAL PROTECTION AGENCY OR LOCAL DRAINAGE AUTHORITY); PLANNING PERMISSION (LOCAL PLANNING AUTHORITY); ELECTRICAL CONNECTION (DISTRIBUTION NETWORK OPERATOR); LEASES; POWER PURCHASE AGREEMENTS, ETC, ETC . . . DETAILED DESIGN & COSTING: CIVIL, HYDRAULIC, MECHANICAL AND ELECTRICAL DESIGN; EQUIPMENT SPECIFICATION; TENDERING / FINAL QUOTATIONS; FINANCE INSTALLATION & COMMISSIONING: CIVIL WORKS; MECHANICAL & ELECTRICAL INSTALLATION; COMMISSIONING OPERATION: ROUTINE CHECKS; PLANNED MAINTENANCE; UNPLANNED MAINTENANCE; ADMINISTRATION; DECOMMISSIONING

1. WHICH TECHNOLOGY?

2. WHAT TO CONSIDER WHEN INSTALLING FROM THE FEASIBILITY STAGE: HEAD & FLOW; FIT DATES; EXISTING INFRASTRUCTURE FROM THE PERMISSIONS STAGE: ABSTRACTION LIMITS; WORKING IN THE RIVER ENVIRONMENT; ELECTRICAL CONNECTION FROM THE DESIGN STAGE: TURBINE, PENSTOCK, INTAKE AND CONTROL SYSTEMS TYPES; ACCESS FOR THE OPERATION STAGE: ROBUSTNESS; FLOODS; MONITORING; PLANNED MAINTENANCE; UNPLANNED MAINTENANCE

2. WHAT TO CONSIDER WHEN INSTALLING FROM THE FEASIBILITY STAGE: HEAD & FLOW; FIT DATES; EXISTING INFRASTRUCTURE FROM THE PERMISSIONS STAGE: ABSTRACTION LIMITS; WORKING IN THE RIVER ENVIRONMENT; ELECTRICAL CONNECTION FROM THE DESIGN STAGE: TURBINE, PENSTOCK, INTAKE AND CONTROL SYSTEMS TYPES; ACCESS FOR THE OPERATION STAGE: ROBUSTNESS; FLOODS; MONITORING; PLANNED MAINTENANCE; UNPLANNED MAINTENANCE

2. WHAT TO CONSIDER WHEN INSTALLING FROM THE FEASIBILITY STAGE: HEAD & FLOW; FIT DATES; EXISTING INFRASTRUCTURE FROM THE PERMISSIONS STAGE: ABSTRACTION LIMITS; WORKING IN THE RIVER ENVIRONMENT; ELECTRICAL CONNECTION FROM THE DESIGN STAGE: TURBINE, PENSTOCK, INTAKE AND CONTROL SYSTEMS TYPES; ACCESS FOR THE OPERATION STAGE: ROBUSTNESS; FLOODS; MONITORING; PLANNED MAINTENANCE; UNPLANNED MAINTENANCE

2. WHAT TO CONSIDER WHEN INSTALLING FROM THE FEASIBILITY STAGE: HEAD & FLOW; FIT DATES; EXISTING INFRASTRUCTURE FROM THE PERMISSIONS STAGE: ABSTRACTION LIMITS; WORKING IN THE RIVER ENVIRONMENT; ELECTRICAL CONNECTION FROM THE DESIGN STAGE: TURBINE, PENSTOCK, INTAKE AND CONTROL SYSTEMS TYPES; ACCESS FOR THE OPERATION STAGE: ROBUSTNESS; FLOODS; MONITORING; PLANNED MAINTENANCE; UNPLANNED MAINTENANCE

3. GOVERNMENT INCENTIVES AND ROI System size:

Feed in Tariff (FiT) from 01 April 2013:

≤ 15 kW

21.65 p/kWh

> 15, ≤ 100 kW

20.21 p/kWh

> 100, ≤ 500 kW

15.98 p/kWh

> 500, ≤ 2 MW

12.48 p/kWh

> 2 MW

3.23 p/kWh

System size:

Export Tariff from 01 April 2013:

All

4.64 p/kWh

3. GOVERNMENT INCENTIVES AND ROI System size:

Feed in Tariff (FiT) from 01 April 2013:

Capital cost:

Internal Rate of Return (IRR):

5 kW

21.65 p/kWh

£ 50 - 100,000

-15 to 5 %

≤ 15 kW

21.65 p/kWh

25 kW

20.21 p/kWh

£ 150 - 350,000

0 to 10 %

50 kW

20.21 p/kWh

£ 300 - 700,000

5 to 10 %

100 kW

20.21 p/kWh

£ 500,000 - 1,500,000

5 to 15 %

> 15, ≤ 100 kW

20.21 p/kWh

500 kW

15.98 p/kWh

£ 2 – 3,000,000

10 to 15 %

> 100, ≤ 500 kW

15.98 p/kWh

> 500, ≤ 2 MW

12.48 p/kWh

> 2 MW

3.23 p/kWh System size:

Export Tariff from 01 April 2013:

All

4.64 p/kWh