INFLOW AND INFILTRATION REDUCTION

Report 2 Downloads 90 Views
INVESTING INFLOW AND INFILTRATION REDUCTION

IN

PROJECT AREA

Blue River South Area 4 Project

Field Crews Working May 2015 - January 2016

YOUR INVESTMENTS AT WORK

INFILTRATION AND INFLOW REDUCTION Blue River South Area 4 Project WHO?

WHAT? • Important field investigations of the sanitary collection system in your area.

WHY? • Investigate the existing sewers to determine locations of needed sewer repairs.

• Kansas City Water Services assisted by GBA, Dubois Consultants, Schmitz King & Associates, and TREKK Design Group.

WHERE? The project is located in Kansas City, Missouri within the following boundaries:

• Reduce risk and frequency of sanitary

• Northern boundary: 85th Street

overflows and basement backups.

• Southern boundary: 109th Street

• Rehabilitate the aging sewer system.

• Eastern boundary: Woodland Avenue

• Meet regulatory requirements as part

• Western boundary: State Line Road

of KC’s Overflow Control Program.

WHAT TO EXPECT? • Various field crews inspecting manholes and cleaning the public sewer lines.

• Smoke from smoke testing activities. • Temporary street closures. • Public meeting will be held to inform property owners about the field investigations and project schedule.

• Crews may knock on your door if they need to inspect the sewer or manholes on your property.

• Crews will not ask to enter your home or building.

IMPROVEMENTS?

WHEN? • Field investigations will be on going through January 2016.

• Design professional services will be conducted from February 2015 through November 2016.

• Construction will occur between March 2017 to March 2019.

• Current activity includes identifying needed sewer rehabilitation repairs.

CONTRACT AMOUNT Design professional services contract includes all services rendered through the construction phase of the project.

• $1,200,000

QUESTIONS? Specific questions about this project can be directed to: • Julie Jenson, Project Manager, KC Water Services, 816-513-0446, or [email protected] • Gary Beck, Project Manager, GBA, 913-577-8216, or [email protected]

www.kcwaterservices.org

• Benjamin Grover, Field Crew Coordinator, GBA, 913-577-8388