Dilley ISD – 2013 Bond Program Project Update Report Septem ber 14, 2016 P rofessional Services Contracts o Program Management - TASB/SE: § Executed 5/5/13 § Work on-going – construction phase
o Architect – BWA: § Executed 2/20/13 § Work on-going – construction phase § Architect of Record - Jay Boynton; Lee Osborne o Survey – Aerial - Geodetics: § Approved by Board 8/29/13 § Work complete and submitted to ISD 10/18/13 o Survey – Topographic and Boundary – Rothe Survey: § Approved by Board 11/18/1 § Boundary Surveying 100% complete § Supplemental Topographic Survey -100% Complete o Geotechnical – Terracon: § Approved by Board 12/16/13 § Final Reports submitted to Design Team – High School 3/27/14 and Elementary 3/19/14
§ Material Testing executed o Asbestos Sampling – TASB/CAM Environmental/Champion Environmental: § Sampling test results complete § Asbestos Consultant – CAM Environmental Phase 1 § Phase 2 scope for Summer 2015 complete. §Elem – 5th Grade Building – work completed April 2016 o Asbestos Consultant / Contractor: § Award of Phase 1 scope to Jupe Environmental at 11/5/14 meeting § Phase 2 work completed by Jupe Environmental § Elem – 5th Grade Building – work completed April 2016 o Construction Manager-At-Risk (CMR) – Gallagher Construction: ____________________________________________________________________________________ 1 (bold items represent update from previous report) Dilley ISD | 9/14/16 Project Update
§ Contract approved by Board § GMP approved by Board in February and amendment executed o Off-Site Water Line – Engineering Design – KSA Engineers, Inc.; General Contractor - RAMII: §Project Complete §Letter to City prepared to transmit closeout documents §Warranty Phase; Operation and Maintenance by City
Design Developm ent / Construction Docum ents o High School and Elementary School Scope Included: i. Elementary campus will remain as-is. ii. HS will not include remodel of existing high school spaces for MS iii. High School does not include culinary arts finish out iv. HS not include parking, drives, Field House, and areas north of the new HS v. HS includes HVAC control system, 3rd science room, and batting cages P roject B udget o Current invoicing tracking spreadsheet maintained by TASB/SE o Updated for current August 2016 invoices received to date. P roject Schedule o 3/9/15 – Pre-construction conference completed. o 3/16/15 - Mobilization and Construction o Substantial Completion Dates - Move-In Summer-2016 (July per current plan) o Detailed schedule by Gallagher o Elementary School §Punch list inside has been completed except one room used for technology (will be inspected prior to school starting). §Exterior – preliminary punch list provided; need resolution of all and final inspection. o High School §Classrooms, Admin, Gym, and Main Corridor have been occupied. §Gym punch list generated. §Cafeteria, Stage, Kitchen, Band pending completion. Anticipated by 10/1. o Punch list items remain for ES or HS; work completed outside of school hours so contractors and students do not mix!
Construction: o Portable Building Lease – Mobile Modular: § Delivered 7/8/14. § Removed July 2016