Submittal #15000-001.0 15000 - HVAC HITT Contracting Inc. 2900 Fairview Park Drive Falls Church, Virginia 22042 Phone: (703) 846-9000 Fax: (703) 846-9110
Project: Capital One - Silverline 7900 Westpark Drive McLean, Virginia 22102
TRANSMITTAL Product Data CRAC 11-1
SPEC SECTION:
15000 - HVAC
CREATED BY:
Ryan Hardey(HITT Contracting Inc. - HQ)
STATUS:
Submitted
DATE CREATED:
03/24/2016
ISSUE DATE:
03/24/2016
REVISION:
0
RESPONSIBLE CONTRACTOR:
The Severn Group - VA
RECEIVED FROM:
Chris Petrakes
RECEIVED DATE: 03/24/2016
SUBMIT BY:
03/24/2016
FINAL DUE DATE: 03/31/2016
LOCATION:
TYPE:
COST CODE:
Product Data
BALL IN COURT: Bradley Brogdon (Gensler - NC Charlotte) DISTRIBUTION: Jay Yeman (Dunlap & Partners Engineers, PC ), Roy Sebring (McKinney & Company), Jim Collins (Gensler - NC Charlotte), Ally Cardamone (HITT Contracting Inc. - HQ), Jonathan Blair (Gensler - DC) DESCRIPTION: **Please see attached CRAC 11-1 ** Please return to HITT with all comments no later than 03/31/2016. Roy - Please make sure to send all of your comments to Bradley so he can input them into Procore ! ATTACHMENTS: 15000-01 Severn Group (Liebert Unit).pdf
SUBMITTAL WORKFLOW
# 1
NAME Bradley Brogdon
BY
HITT Contracting Inc.
SUBMITTER/ APPROVER
SENT DATE
DUE DATE
Approver
3/24/2016
3/31/2016
DATE
RETURNED RESPONSE DATE
ATTACHMENTS
COMMENTS
Pending
COPIES TO
Page 1 of 2
Printed On: 03/24/2016 04:58 PM
2900 Fairview Park Drive HITT Contracting Inc. Falls Church, Virginia 22042
SUBMITTAL COVER SHEET Capital One - Silverline
Owner:
General Contractor: HITT Contracting
Designer:
Subcontractor: The Severn Group - VA
MEP Engineer:
Interior Designer:
Structural Engineer:
Submittal
Rev.
Description
Submitted For:
15000-001
0
Product Data CRAC 11-1
Review & Approval
General Contractor's Approval:
Engineer's Approval:
Consultant's Approval:
HITT CONTRACTING INC CAPITAL ONE - SILVERLINE
REVIEWED
REVIEWED AS CORRECTED
REVISE AND RESUBMIT
REJECTED
FOR INFORMATION ONLY
Reviewed in accordance with AIA 201 and the Contract Documents. This submittal is in full compliance with the Construction Documents except as explicitly noted.
BY: Ryan Hardey
DATE: 3/24/2016
SUBMITTAL #
DESCRIPTION
15000-001 Product Data CRAC 11-1
SUBMITTAL REVIEW
Architect's Approval: NO EXCEPTIONS TAKEN. MAKE CORRECTIONS AS NOTED. Resubmittal not required unless Contractor cannot comply with corrections noted. REVISE AS NOTED AND RESUBMIT. RESUBMIT PROPERLY. Submittal not reviewed for reasons noted. NOT REVIEWED. Submittal not required by Contract Documents. RECEIVED FOR CLIENT’S RECORD ONLY. Submittal not reviewed.
Gensler has reviewed this Submittal, but only for the purpose of checking for conformance with the design intent expressed in the Contract Documents. Gensler’s action on a specific item does not indicate approval of an assembly of which the item is a component, nor of an item as delivered and installed if it does not conform to the Contract Documents. Contractor is responsible for checking for deviations between this Submittal and differing information or conditions in the Contract Documents and field conditions; for determining or substantiating the accuracy and completeness of other details such as dimensions and quantities; for substantiating instructions for installation or performance of equipment or systems designed by Contractor; for construction means, methods, techniques, schedules, sequences, procedures, and fabrication processes; for errors and omissions in Submittals; for coordination of the Work of the trades, safety precautions and performing the Work in a safe and satisfactory manner and in conformance with the Contract Documents. If more than one submittal review stamp appears on this Submittal, the most stringent action and notations thereon apply. Signature of a submittal review stamp by Gensler or a consultant does not imply that it has reviewed work not within its professional discipline or scope of services.
By:
v1 3/2012
Brad Brogdon
Project No: 09.8337.000 Submittal:
15000-001
See McKinney comments.
Date: Wed Mar 30, 2016
Submittal Data Date: 03-30-2016 Roy Sebring McKinney and Company 100 South Railroad Avenue Ashland, VA 23005
A B C
RE:
15196 Capital One Project Y
D
ACTION CODE No exceptions taken. Make corrections to exceptions noted. Resubmittal not required. Make corrections to exceptions noted and resubmit. Not in compliance with contract documents. Rejected.
WE ARE SENDING YOU: Qty
Submittal Date
Spec. No.
Action
1
3/30/16
238123
B
Description CRAC Units
Review of this data is only for conformance with the design concept as given in the Contract Documents. The Contractor is responsible for: quantities, functions, dimensions and coordination of the work with other trades COMMENTS:
Delete floor stand accessory. Provide dual-float condensate pump. Provide 18" high supply air discharge plenum with 2/way grilles (front and left when facing the unit).
Jay C. Yeman, PE Senior Mechanical Engineer Copy to:
MECHANICAL•ELECTRICAL•PLUMBING•FIRE PROTECTION 2112 W. Laburnum Avenue, Suite 205; Richmond, VA 23227 • 804-358-9200 Telephone • 804-358-2928 Facsimile • ww.DunlapPartners.com
15097 - 238123 - CRAC Unit Comments (Rev 0).xls