inflow and infiltration reduction

Report 9 Downloads 71 Views
INVESTING INFLOW AND INFILTRATION REDUCTION

IN

PROJECT AREA

Blue River South Area 3 Project

Field Crews Working May 2015 - November 2015

YOUR INVESTMENTS AT WORK

INFILTRATION AND INFLOW REDUCTION Blue River South Area 3 Project WHO?

WHAT? • Important field investigations of the

• Kansas City Water Services assisted

sanitary collection system in your area.

by Olsson Associates, Taliaferro & Browne, and TREKK Design Group.

WHAT TO EXPECT? • Various field crews inspecting manholes and cleaning the public sewer lines.

• Smoke from smoke testing activities.

WHY? • Investigate the existing sewers to determine locations of needed sewer repairs.

• Reduce risk and frequency of sanitary overflows and basement backups.

WHERE?

• Temporary street closures.

The project is located in two areas of Kansas City, Missouri within the following boundaries:

• Public meeting will be held to inform

• Northern boundary: Red Bridge Road • Southern boundary: Kenneth Road

• Rehabilitate the aging sewer system.

• Eastern boundary: 71 Highway

• Meet regulatory requirements as part

• Western boundary: State Line Road

of KC’s Overflow Control Program.

property owners about the field investigations and project schedule.

• Crews may knock on your door if they need to inspect the sewer or manholes on your property.

• Crews will not ask to enter your home or building.

IMPROVEMENTS?

WHEN? • Field investigations will be on going through November 2015.

• Design professional services will be conducted from January 2015 through August 2016.

• Construction will occur between December 2016 to February 2018.

• Current activity includes identifying needed sewer rehabilitation repairs.

CONTRACT AMOUNT Design professional services contract includes all services rendered through the construction phase of the project.

• $380,000

QUESTIONS? Specific questions about this project can be directed to: • Julie Jenson, Project Manager, KC Water Services, 816-513-0446, or [email protected] • Kevin Waldron, Project Manager, Olsson Associates, 816-361-1177, or [email protected]

www.kcwaterservices.org

• Ed Eilers, Field Crew Coordinator, TREKK Design Group, 913-230-8694 or [email protected]